Water System Plan - 2013

This Water System Plan (WSP) for the Public Utility District No. 1 of Skagit County has been developed according to Washington Administrative Code (WAC) 246-290-100, which requires that public water systems submit a water system plan to the Washington State Department of Health (DOH) every 6 years.

The 20-year planning horizon for this plan is 2014 to 2033. At the pre-planning meeting with DOH, it was agreed that this plan update would focus on the PUD's Judy Reservoir System. The PUD's eight satellite systems were included in the 2007 plan and, with little change since that time, there was no need to update the planning figures. However, a summary of the satellite systems isĀ provided in Chapter 12.